  • AutoCAD Training Center (ATC) Ltd, Dhaka, Bangladesh. Diploma in CAD System, Diploma in CAD System, Course successfully completed 2003 – 2004
  • Genetic Computer School” (Singapore) Bangladesh Branch Computer Management in Windows, MS-Word, MS-Excel, and MS-FoxPro, Course successfully completed 1995 – 1995
  • Bangladesh Air Force Shaheen College, Dhaka Higher School Certificate Examination, Science, 2nd Division 1988 – 1989
  • AutoCAD Training Home (ATH). AutoCAD 2D, AutoCAD 2D under Release 14 & 2000, Course successfully completed 1987 – 1988

Other experience

  • Position: Data Entry Supervisor Duration: 01-Oct.-1995 to 30-Nov.-1996
    Organization: North American Computing Dynamics Incorporated, 5 Mohakhali C/A (7th Floor), Dhaka-1212, Bangladesh
    Responsibility: My major responsibilities are
    1. Supervision of Data Entry & Data Processing
    2. Oversee of Data Browsing & Data Control Operations
    3. To maintain file server (Novel Netware 3.11)
  • Position: AutoCAD/GIS Operator Duration: 01-Dec.-1996 to 31-Jan.-2005
    Organization: CosmoSoft Systems, House 16 (3rd Floor), Road # 27, Block # J, Banani, Dhaka-1213, Bangladesh.
    Responsibility: Developing the drawings/MAP by following the instruction and guideline given by AutoCAD/GIS Supervisor and make correction if asked by the AutoCAD/GIS Supervisor.
    At the Same time another Project Executed at CosmoSoft Systems Under my Supervision is the Data-Entry of consumer listing Dhaka Electricity Supply Authority (DESA) in cooperation with Associates Resource Management Company (ARMCO).
  • Position: Supervisor (AutoCAD/GIS) Duration: 01-Feb.-2005 to 21-Apr.-2011
    Organization: CosmoSoft Systems, House 16 (3rd Floor), Road # 27, Block # J, Banani, Dhaka-1213, Bangladesh.
    Breakdown list of job type/Responsibility:
    a. My job is to edit the images and scale all sorts of raster drawings (including GIS map and positioning the map under proper GEO projection).
    b. Store the ready for working jobs in server.
    c. Organize the work segment-wise and distribute to AutoCAD/GIS operators through in house network protocol.
    d. Troubleshooting the work if any problem arises during developing drawings/MAP.
    e. Edge match and integrate the whole drawings/MAP.
    f. Check the drawings/MAP layer wise and make correction if necessary.
    g. Organize and save the completed job in Ready to deliver the folder in the server.
    All AutoCAD/GIS jobs are supplied by our offshore clients (Clients are from Australia, Switzerland, Canada & USA). Client supplies this entire job on TIF / TIFF / JPG / PDF etc. format. We design on that image and supplied on DWG / DXF / DWT / DGN / SHP etc. format. We receive Raster Image of Architectural Plan/Elevation/Section/Detail & Site Plan, Circuit Design/Diagram, Mechanical design, Electrical design & GIS Contour Map/Roads & utility Map/Arial photography. We convert it to AutoCAD 2D DWG / DXF / DWT / DGN / SHP etc.
    Basically, I maintain all AutoCAD/GIS operator and give them the backup with instructions and edit their work on behalf of client’s requirements.
  • Position: Draftsman/AutoCAD Operator Duration: 25-Apr.-2011 to 31-Mar.-2014
    Organization: ABDULLAH A.M. ALKHODARI SONS COMPANY, Mazen Al Saeed
    Business Tower, P.O. Box 3589, Al-khobar 31952, Saudi Arabia
    Project: Construct Above & Underground Piping Project (World Biggest & Saudi Arabia first Aluminium smelter),
    Ma’aden Aluminium Smelter, Ras Al-Khair
    Consultant: BECHTEL
    Client: Saudi Arabian Mining Company (MA’ADEN)
    Breakdown list of job type/Responsibility:
    a. Preparing general layout (Aboveground & Underground) of Fire water, Potable water, Process water, Blow down water, Irrigation water, Storm water, Waste water, Compressed Air & Natural Gas line drawings& merge 84 drawings sheet together as per Easting Northing coordinates.
    b. Preparing general layout Sewage sanitary, Manhole & Pump station drawings & merge 8 drawings sheet together as per Easting Northing coordinates.
    c. Preparingmanhole shop drawing & calculate Height of 102 manholes& order to vendor for manufacturing manhole.
    d. Preparing Excavation section (As per IFC drawings & existing ground level) & prepares all documents to submit Bechtel “Excavation permit” for laying pipes.
    e. Preparingmaterial list: length of pipes as per diameter & quantity of Fire water valve, Fire Hydrant, Potable water valve, Process water valve, Blow down water valve,
    f. Preparing Fire water Stainless Steel Spool length& order to fabrication shop for fabricating spool.
    g. Preparingpiping reroute/proposed plan & profile drawings as per site clashing with existing foundation, drain, culvert, etc. depends on survey data from the surveyor.
    h. Preparing weekly progress report for Sewage & Sanitary Systems, Pump station & culverts, Fire water, Potable water, Process water, Blow down water, Compressed Air & Natural Gas line.
    i. Preparingdrawings for Potable water & Process water valve spool stainless steel drawings & order to fabrication shop for fabricating spool.
    j. Preparing As Built drawings for closing excavation permit as per survey report from the surveyor.
    k. Preparing Isometric drawings & material lists for Storm water Stainless steel pipes.
    l. Preparing Bollard list as per drawings & request additional Bollard list as per site condition.
    m. Preparing As Built Drawings (Easting Northing coordinates with elevation) of Fire water, Potable water, Process water, Blow down water, Natural gas, Compressed Air, Storm water, Sewage sanitary, Manhole & Pump station as per survey report.
    At the Same time, I had finished another Project at Ras Al-Khair. “KHODARI LABOR CAMP”with below responsibilities:
    a. Preparing concept and presentation drawings from sketches.
    b. Preparing general layout drawings
    c. Preparing working drawing that includes working plans of Site Manager, Construction Manager, Site Engineer, Engineer/Technician, Foreman, Labor, Gourd Room, Clinic, Camp Boss, Laundry, Engineer & Foreman Recreation, Engineer’s Dinning, Foreman & Labor Dinning, Mosque, Labor toilet block potables.
  • Position: Draftsman / AutoCAD Operator Duration: 01-Apr.-2014 to 31-Oct.-2014
    Organization: ABDULLAH A.M. ALKHODARI SONS COMPANY, Mazen Al Saeed
    Business Tower, P.O. Box 3589, Al-Khobar 31952, Saudi Arabia
    Project: Operation and Maintenance of road Network in Ras Al Khair Kingdom of Saudi Arabia
    Client: Royal Commission for Jubail &Yanbu- Jubail Kingdom of Saudi Arabia
    Breakdown of job type/Responsibility:
    Prepare Roads drawings/sketches (Plans and sections) for repair and revise work as per RC instruction.
  • Position: Secretary of DIIP Duration: 01-Nov.-2014 to 18-Feb.-2021
    Organization: ABDULLAH A.M. ALKHODARI SONS COMPANY, Mazen Al
    Saeed Business Tower, P.O. Box 3589, Al-Khobar 31952, Saudi Arabia
    Project: 1. Umm Wu’al Phosphate Project - U&I at Umm Wu’al Well Field
    Package - 14-KB-042 (EPC Contract) & Al Khodari Camp (Project Awarded on 10 February 2015)
    2. Smelter Pot Relining Facility at Ma’aden Aluminum Ras Al Khair (Partial EPC Contract and Project awarded on 28 June 2016)
    Consultant: Jacobs and Hatch
    Client: Ma'aden Wa'ad Al Shamal Phosphate Company, Turaif and Ma'aden Aluminium company, Ras Al-Khair
    Breakdown list of job type/Responsibility:
    Secretary of Director Industrial & Infrastructural Projects (DIIP), A link between Project Site Offices and various Departments i.e.
     Coordinate with HR for mobilize and demobilize employees as per projects requirements and follow-up for exit settlement for exit employees.
     Coordinate with Passport & Personnel Department for IQAMA renewal, Vacation, Exit and Termination.
     Coordinate with suppliers for getting Quotation for Materials, upon approval of COO send request to Procurement Department for prepare PO.
     Coordinate with Finance Department for follow-up suppliers Invoices& Payment, Project expenses & Petty cash.
     Coordinate with Payroll Department for prepare payroll for the projects employees.
     Coordinate with EMD Department (for Equipment and vehicle) for Equipment’s and Vehicles for projects.
     Coordinate with Logistic Department for Delivery Materials from Alkhodari Main store or supplier warehouse to projects.
    Also Involved all Bid Documents received and forward to Tendering Department, subcontractors and suppliers to get their Technical and commercial proposal and in Preparation submission of Technical and Commercial Bid Proposal of Bechtel, Jacobs, Fluor, Ma’aden, Royal Commission, Samsung, Hatch and Amec Foster. Send Technical and commercial clarification / Query for Pre Bid and Post Bid and arrange free pre Bid Meeting (Site Visit)
    As a Draftsman/AutoCAD Operator, I had prepared for Well Field Package Project 64KM Transfer Pipeline, Substation, Booster station and 26KM Well Field Area Layout drawing as per Bid Drawings. Additionally I had prepared 64KM Transfer pipeline profile drawings with shown existing ground level and Proposed Invert Trench Excavation level for as per Engineering design company (Al-Khodari Subcontractor). At the same time I had prepared Site Construction Camp Layout Drawings, Camp Capacity more than 1200 persons (different categories).
    In addition I was involved as a Lead Document Control for Engineering Design Drawings and Technical submittal (30%, 60%, 90% and 100%) received from our Engineering subcontractor and submit Jacobs through email from Head office after checking Drawings and Documents number and title. After receiving Jacobs comments forwarded to Design Subcontractors for rectify / modify for next submittal.
  • Position: Draftsman Duration: 19-Feb.-2021 to 28-Feb.-2023
    Organization: Sinosteel Equipment& Engineering (Saudi Arabia) Co. , Ltd.
    305-306, Ababtain Tower, Dhahran St., Al-Khobar, Saudi Arabia
    Project: SABTANK ADMIN BUILDING PROJECT (AF-1135054)
    Jubail Port, Al-Jubail, KSA
    Client: Saudi Basic Industries Corporation (SABIC)
    Breakdown list of job type/Responsibility:
    Preparing Shop drawings and revised IFC drawings (Civil, Architectural, Structural, Electrical, Mechanical and Plumbing) as per Site/SABIC requirement and submit to SABIC for approval and also prepared AS-BUILT RED LINE drawings of all disciplines.