Cementing Check Throttle Valve
The customer supplied the required external appearance and overall dimensions. The task was to develop the complete product design for operation under pressure, temperature, dynamic loading, and corrosive-environment constraints.
The project included:
• 3D mechanical modeling
• Internal assembly and flow-path development
• CFD analysis within the customer-defined operating conditions
• Structural assessment within the agreed scope
• Material selection against the specified operating constraints
• Preparation of manufacturing documentation for a cast product
My role covered product design, CAD development, preparation and transfer of engineering documentation, and participation in prototype acceptance. The engineering stage was completed in 14 days. Manufacturing, testing, and certification were outside this project duration.